407A component is scheduled to close at the end of the week .What should the program manager verify prior to allowing the component to close?
选项:
A: The component has released resources to meet program objectives
B: The component has met the quality requirements to meet program objectives
C: The component has met the schedule requirements to meet program objectives
D: The component has met the benefits realization criteria to meet program objectives