You have been working on your project for 6 months and have just finished eliciting all of the requirements. A review is scheduled in 2 weeks to ensure you have a solid understanding of your stakeholders' requirements before they are baselined. What do you have at this point as an input into there view?
选项:

A:Specified and modeled requirements
B:Stakeholder concerns
C:Unconfirmed elicitation results
D:Confirmed elicitation results

发布时间:2024-05-14 19:16:31
推荐参考答案 ( 由 搜题小帮手 官方老师解答 )
联系客服
答案:

以下文字与答案无关