In the following expressions about the construction cost analysis method,which is wrong
选项:
A:Factor analysis method is also known as serial replacement method
B:When the factor analysis method is adopted, the ranking rule of its indicators is: value quantity first, goods quantity later; the absolute value first, the relative value later
C:Factor analysis method can be used to analyze the impact of each factor on cost
D:The comparison method is called the comparative analysis of indicators
发布时间:2024-06-09 00:40:15